1)

Your sponsor is asking for a review, of your project and you start collecting the details and started the reports needed to present to the sponsor. You find you are 3 days behind schedule. The project estimated finish date is still 4 months away. You think you can cover up the delay by adjusting the tasks. What should you do now when reporting the project status to the sponsor?





B



      